Steps | Work Detail | Machine Detail | Specificationmake Model | Capacity(Per Shift 8 Hrs) |
---|---|---|---|---|
III) | Density Wise Separation for categorized (01qty) | Purpose – Sort plastic , screen less than 130mm and pass further to next process Capacity – 30 TPH | ||
A)Screening of material forsize of 4- 6MM | Bio Soilsegregation for Farmers of landfilling | Per Shift 800 MT | ||
A) Low Density material separated Plastic | Motor – 25 HP, 3 Phase Material Of Infra – SS and MS Material in Kg – 4.9 Tones Dimension - 3 m X 2.5m X 2 m | RDF | Per Shift 800 MT | |
B)High Density material (Recycling and Inert) | Inert for RDF | Per Shift 800 MT | ||
IV) | Magnetic Separator (01qty) | Purpose – Sorting metal from waste Capacity – 90 kg at a time Motor – 2 HP Dimensions – 1 m X 2 m X 1.6 m | Iron material separation | Upto 100 KG from 1.5 Mtr |
V) | Shredding of RDF (03 Qty) | Purpose – Shred RDF Capacity – 25 TPH Motor – 60 HP Dimension – 3 m X 2.5 m X 2 m | Plastic Shredding as RDF for Respective Industrial Customer | |
VI) | Bailing (04 Qty) | Purpose – RDF Baling Capacity – 20 TPH Motor - 30 HP Power – Hydraulic Power, 40 Tone Dimension – 3m X 3m X 2m | Compress Recyclable material to reduce volume | Per Shift 400 MT |
VII) | Zatak (Plastic Cleaning machine) (02Qty) (01Qty) | Purpose – Plastic bag cleaning material Capacity – 20 TPH Motor – 15 HP, 3 Phase Dimension – 3m X 3m X 2m | Per Shift 250 MT |
Sr.No. | Activity | Frequency | Capacity(Per Shift 8 Hrs) | Start Time | Completion Time |
---|---|---|---|---|---|
1) | Mining of Dumpsite | Daily Basis | Per Shift 1500MT | Immediate Basis | With in Starting 2 Months |
2) | Hipping of Legacy waste | Daily Basis | Per Shift 1200MT | Immediate After Mining | With in Starting 2 Months |
3) | Bio Culture Treatment | Daily Basis | Per Shift 1500MT | Immediate with Hipping | With in Starting 2 Months |
4) | Bio Mining Plant Installment and Commissioning (Including Civil, Machine Installation, Infra) | One Time | 1000 TPD | Immediate | 3 Months |
5) | Mechanical Separation | Daily Basis | Per Shift 800MT | After 3 Months | With in 3 Months |
6) | Disposal of RDF (Dispatch to respective Industry) | Daily Basis | Per Day 300 MT | On time | With in Week disposed |
7) | Disposal of Recyclable material | Daily Basis | N/A | After Vehicle Load generated | With in Week Disposed |
8) | Disposal of Inert | One Time | 300TPD | Immediate | After Completion of Screening |
Sr.No. | Equipment/Implement | Quantity | Replacement Frequency | Capacity/Make |
---|---|---|---|---|
1) | Excavator | 04 | N/A | JCB 210 |
2) | Loader | 02 | N/A | - |
3) | Bio Culture Spraying Machine | 02 | N/A | - |
4) | Fire Fighting System | N/A | N/A | - |
Sr.No. | Vehicle Type | Owned Numbers | Leased Numbers | Total Number | Capacity in Terms Of Volume |
---|---|---|---|---|---|
1) | Dumper | 0 | 10 | 10 | 4 Brass Each |
2) | Loader | 0 | 2 | - | - |
3) | Site Van | 0 | 01 | - | 7 Seater MPV |